How Long Does It Take to Build a Custom Home in Ontario? 

Architect At A Construction Site Looking At A Blueprint Using An Interactive Screen - How Long Does It Take to Build a Custom Home in Ontario?

Designing your dream home? Then you might be wondering how long you'll have to wait to make it a reality. To that, we say good things take time and you'll have to be patient when constructing a custom home in Ontario. Luckily, there are ways to ensure the project proceeds as efficiently as possible. Keep reading to learn more about custom-build timelines and the factors that affect them.

How Long it Takes to Build a Custom Home in Ontario

If you're considering building a custom home, it's important to have a realistic timeline in mind. On average, it takes about 10 to 16 months to construct a custom home in Ontario. Factors such as the size and complexity of the project, availability of materials, and even weather conditions can affect the timeline. 

4 Factors That Affect the Timeline of Building a Custom Home: 

  • Size and complexity of the project: Larger homes with intricate designs and unique features may take longer to complete than smaller, more straightforward builds. 
  • Availability of materials: Certain materials may be difficult to source or experience delivery delays, which can impact the project's timeline. 
  • Weather conditions: Extreme weather events like heavy rain or snow can halt construction and extend the build time.  

Understanding What Happens at Each Stage

Building a custom home involves several key stages. The initial design phase can take 1-2 months, during which architects and designers create the blueprints. Obtaining permits from local authorities usually requires an additional 1-3 months. The construction phase, which includes site preparation, foundation work, framing, plumbing, electrical, and finishing, typically spans 6-12 months. Regular site inspections and adjustments based on client feedback are common throughout the process. Effective communication with your builder ensures that each stage progresses smoothly and on schedule.

Home Building Timeline Example

  1. Initial Design Phase: 1-2 months
  2. Securing Permits: 1-3 months
  3. Construction Phase:
    • Site Preparation: 1-2 weeks
    • Foundation Work: 2-4 weeks
    • Framing: 1-2 months
    • Plumbing and Electrical: 1-2 months
    • Finishing (interior and exterior): 2-3 months
  4. Final Inspections and Adjustments: 1-2 weeks

This may vary slightly depending on the work you want done, the size of the home, and other factors listed above. Be sure to get a clear timeline from your home-building contractor before you sign any agreements.

Work With the Experienced Builders at Team Shane  

If you're ready to build your custom home in Ontario, Team Shane is your top choice. Our experts can guide you through the process and ensure that your custom home build is completed efficiently and to your satisfaction. Contact us today to get started! 

Resources

Questions?
Ask Team Shane 

At Team Shane, we have a team of designers that work directly with clients to create beautiful home designs while providing advice and direction on selections (interior design) and up-to-date cost implications which will help you make decisions for the final design. Our build team takes those designs and makes them a reality.
View FAQs
Join our mailing list
This field is for validation purposes and should be left unchanged.